Caroli says Esplanade dispute costs State €1.5m monthly
By Zak Jackson, MonacoViews Editorial
Groupe Caroli has demanded €210 million from the Monegasque State over the stalled Esplanade des Pêcheurs project, warning that delays are costing public funds €1.5 million each month.
Groupe Caroli has escalated its long-running dispute with the Monegasque State over the abandoned Esplanade des Pêcheurs redevelopment, issuing a statement on Thursday that puts the cost of continued delay at roughly €1.5 million a month in public funds. The developer is seeking €210 million in compensation after the project, once earmarked for the waterfront site near Fontvieille, was shelved.
The statement came in response to a recent Supreme Court ruling on the matter, with Caroli Immo signalling it intends to keep pressing the State for payment rather than let the dispute lapse. For residents and businesses near the Esplanade, the stalemate means continued uncertainty over what, if anything, will eventually replace the vacant site.
The case adds to scrutiny of how Monaco's government manages large-scale development disputes, particularly where public money is tied up in projects that stall before completion. With both sides entrenched, the financial clock Caroli describes, now running into tens of millions of euros, is likely to keep the case in the public eye in the months ahead.